A typical request from management is to have a summary of all the work done for a certain time period for a client. So the report basically would look like this:

From Time X - To Time Y

  • Project A - 100.5h
  • Project B - 50.8h
  • Project C - 14h

shridhar-tl commented on Oct 10, 2018

Hi @iraszl , I would implement this functionality ASAP.

shridhar-tl commented on Sep 14, 2019

Implemented as part of #53 and is available for chrome users already.

shridhar-tl commented on Sep 30, 2019

Assuming this is working fine, closing this issue. If their is anything more to be done as part of this issue, this can be reopened or a new issue can be raised.

🟢